Thursday, 17 December 2009

Project lead reflects on 2009 progress

Lunchsat project lead Nick Fishwick has today issued a statement to his team, reflecting progress made in the project throughout 2009.


In an email to all 43 members of the Lunchsat team, Nick gave his congratulations and 'thanks for all the hard work over the last few months'.

"The project is coming along well with real results, such as Systems producing an updated release of the Payload Interface Document which will be critical for getting new payloads and all subsystems have made good advances. On the hardware side, we have power tests ready to go and work planned on both groundstations.


"Due to the feedback from last year, we are communicating better with experts inside and outside the company (such as the Bepi Project Manager, AMSAT, Queen Mary Uni) and the blog is going and we are being tweeted about by Clyde Space [a large Cubesat company in Scotland].


"There have been some setbacks but that is normal for any programme no matter the size and so we should take this as an opportunity to show that we can overcome and solve such problems. We have a plan in place to solve the OBC power-up issue and this will be the highest priority in the New Year."


Visit the Lunchsat website news archives for more Project Management team communications.

Thursday, 10 December 2009

Latest from the Project Management focus team


The Lunchsat Project Management focus team recently issued its latest actions to scope upcoming work packages for the subsystems and classify activities from current progress to the 2012 launch.

Subsystem leads are to supervise the extension of subsystem work package descriptions for completion by February; descriptions for each are to be released on our website pages to assist in the definition of each subsystem.

Those involved are Nick Fishwick (Project Management and Power), Stephen Pulker (On-Board Computer and Imager), Natasha Pushkin (Thermal and ADCS), Alex Buick (Operations and Payload), Jason Stones (Media and Communications), Fatou Mbaye (Systems and Mechanical) and Nicolas Sarda (Groundstations).

The focus team also arrived at a complete schedule that defines Lunchsat activity from present to the future launch. Three work packages are to be defined per subsystem for assignment to each of the three Lunchsat phases that have since been defined (1-3); these are detailed in turn (A-E):

Phase 1: Design and Analysis, October 2009 to September 2010
Phase 2: Testing and Pre-Launch, October 2010 to December 2011
Phase 3: Launch and Operations, 2012

Phase A: Detailed Definition, Manufacturing and Testing (GDP Year 1), October 2009 to August 2010
Phase B: Detailed Definition, Manufacturing and Testing (GDP Year 2), October 2010 to June 2011
Phase C: System Level Integration and Testing, July to December 2011
Phase D: Pre-Launch Activities and Launch, January to June 2012
Phase E: In-Orbit Commissioning and Operations, July to December 2012

The Lunchsat website now features details of our complete schedule.